Steam rises from the huge boiler units at the Jim Bridger Power Plant east of Rock Springs. The power plant could be shut down by year’s end unless it is granted more time to comply with federal haze standards.

PacifiCorp could be forced to shut down one of four coal-burning units at the Jim Bridger power plant at year’s end unless it is granted more time to comply with federal haze standards, according to landowner advocacy group Powder River Basin Resource Council.

Alternatively, the U.S. Environmental Protection Agency could head off a closure by approving proposed revisions to Jim Bridger’s regional haze plan.

Neither PacifiCorp nor the EPA has indicated that a shutdown is imminent.

PacifiCorp, which operates as Rocky Mountain Power in Wyoming, has so far failed to install “selective catalytic reduction” technology at Jim Bridger units 1 and 2 to reduce nitrogen oxide emissions. The pollutant contributes to regional haze. SCR installation is a primary condition of Jim Bridger’s federal emissions permit, PRBRC attorney Shannon Anderson said.

The deadline to install the controls is end of 2021 for Unit 2, and end of 2022 for Unit 1.

Meantime, Wyoming will sue EPA for its alleged failure to act on Rocky Mountain Power’s proposed revisions to the regional haze plan for Jim Bridger, Gov. Mark Gordon said in a Nov. 15 “notice of intent” letter. Those revisions would remove the SCR controls requirement.

Gordon chastised EPA, accusing it of intentionally imposing higher energy costs, undermining grid reliability and threatening Wyoming jobs while working against more effective actions to curb environmental impacts. “And for what?” he wrote EPA. “Shallow talking points on the international stage?”

Rocky Mountain Power believes it will remain in compliance with its federal emissions permit despite not installing the SCR technology, according to a spokesman.

“Our objective continues to be to maintain compliance and operate Jim Bridger units 1 and 2 until 2024, at which time they would be converted to use natural gas fuel,” Rocky Mountain Power spokesman David Eskelsen told WyoFile via email. “We are also committed to work constructively with both the state of Wyoming on their state implementation plan, and with EPA on resolving this regulatory issue.”

The row between Wyoming and EPA over regional haze dates back more than a decade. As the federal agency has revised standards aimed at curbing emissions, Wyoming coal-fired electrical power producers have recalculated the implications of adding emission controls to meet regional haze requirements.

Regional haze, in a regulatory context, is the degradation of visibility via human-caused emissions that diminish the characteristics and enjoyment of a landscape, according to EPA.

EPA’s regional haze program focuses on reducing industrial emissions to help clear viewsheds, particularly in national parks and wilderness areas. The Jim Bridger power plant falls within several “Class 1” regional haze designations, which include Grand Teton and Yellowstone national parks.

That proximity and potential to contribute to diminished viewsheds obligates Jim Bridger’s operator to meet tailored emission standards for nitrogen oxides, sulfur dioxides and particulate matter — the main industrial pollutants that contribute to regional haze.

PRBRC is one of several parties involved in ongoing litigation, as well as negotiations under a 10th Circuit Court of Appeals mediation process. Gordon’s notice of intent to sue EPA indicates those negotiations might not result in a solution anytime soon, Anderson said. Gordon’s notice, and his chastising tone, “just takes us a step backwards from a deal that could be reached.”

Rocky Mountain Power’s proposed alternative would involve operating the coal units at lower capacities, according to Anderson.

EPA has not indicated any deficiencies in the alternative backed by Wyoming and Rocky Mountain Power, Gordon said. Wyoming DEQ reviewed Rocky Mountain Power’s proposal and forwarded it to EPA for its review in May 2020. EPA notified Wyoming DEQ it had reviewed the proposal and gave it initial approval in November 2020, yet the approval was never published in the Federal Register, he said.

“After the change in administrations,” Gordon wrote, “EPA decided to ignore the decision of the Regional Administrator, and reconsider his prior approval.”

EPA intends to issue a proposed decision on this plan revision for public comment in the near future, a spokesman said.

Recommended for you

(0) comments

Welcome to the discussion.

Please note: Online comments may also run in our print publications.
Keep it clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
Please turn off your CAPS LOCK.
No personal attacks. Discuss issues & opinions rather than denigrating someone with an opposing view.
No political attacks. Refrain from using negative slang when identifying political parties.
Be truthful. Don’t knowingly lie about anyone or anything.
Be proactive. Use the “Report” link on each comment to let us know of abusive posts.
Share with us. We’d love to hear eyewitness accounts or history behind an article.
Use your real name: Anonymous commenting is not allowed.
.
The News&Guide welcomes comments from our paid subscribers. Tell us what you think. Thanks for engaging in the conversation!

Thank you for reading!

Please log in, or sign up for a new account and purchase a subscription to read or post comments.